After lunch we strip the forms, clean and stack them, and put all of the stakes in the truck to be cleaned up for the next use… 1:45pm sprinkler running to help the slab cure. It was an easy day for us, but we paid a premium for Saturday delivery

By 11:00 am we’re loosening the stakes in the forms.

I was onsite at 5am taping up the joints in the forms, and coating them with diesel. The first truck arrived about 6:10 am.
Rodney and crew from Monterey are very sharp… 48 ½ yards of concrete are in place by 8:45 am