Sunday, May 21, 2006

Saturday May 20th Poured Slab

After lunch we strip the forms, clean and stack them, and put all of the stakes in the truck to be cleaned up for the next use… 1:45pm sprinkler running to help the slab cure. It was an easy day for us, but we paid a premium for Saturday delivery
By 11:00 am we’re loosening the stakes in the forms.

I was onsite at 5am taping up the joints in the forms, and coating them with diesel. The first truck arrived about 6:10 am.
Rodney and crew from Monterey are very sharp… 48 ½ yards of concrete are in place by 8:45 am